Normalized Story Points

UPDATE: 18 months later, I've reflected back on this topic in my post "Revisiting Normalized Story Points".

I was recently involved in a discussion on LinkedIn on the topic of Normalized Story Points and whether or not it was a good idea. What I noticed was that, despite what I think is a very clear explanation by the Scaled Agile Framework (SAFe), many people misunderstand both the process for normalizing Story Points and the intended benefit to be gleaned from this practice. If you have not yet, I encourage you to read the explanation in the “Iterations” abstract on the Scaled Agile Framework before reading on (the section entitled “Relative Estimating, Velocity and Normalizing Story Point Estimating”). That will provide the proper context for my thoughts, as a Certified SAFe Program Consultant and active Release Train Engineer, on what this means (and what it doesn’t).

First, how do we normalize Story Points? The gist of the process is this:
“1. For every developer tester on the team, give the team eight points (adjust for part timers)
2. Subtract one point for every team member vacation day and holiday
3. Find a small story that would take a about a half-day to code and a half-day to test and validate. Call it a 1.
4. Estimate every other story relative to that one.”
That’s basically it. The primary problem that teams run into is that they ignore step #4, along with the advice that follows these steps: “There is no need to recalibrate team estimating or velocities after that point.” This is a tool that has very specific benefits; it is intended for one-time use that allows for long-term benefit.

This means that teams within a SAFe organization are using a common practice to determine a baseline from which to begin relative estimation and, as such, will have Story Points that are roughly the same size. This will enable “just good enough” Story Point estimation of cross-team Features and Epics, which allows for more precise road-mapping and budgeting than we would otherwise have.

This does not mean that teams are estimating using Ideal Man-Days. They should still do relative estimation using the modified Fibonacci sequence. This also does not mean that roadmaps will be 100% precise; they will simply be more precise than what’s been available before. Budgeting will be precise in the sense that we float scope, not cost; however, the Epic Owner should only expect the Minimum Viable Product (MVP) and not necessarily every requested feature when the Epic has been initially estimated and not yet broken-down.

This means that teams establish how “big” a Story Point is early and don’t have to spend as much time figuring that out as a team. When I first became a Scrum Master, my team ended up having to re-baseline several times as they learned how to better write and slice User Stories. The alternative would have been either User Stories that were smaller than one point or multiple one-point Stories that were considerably variable in the amount of effort they actually required.

This does not mean that all teams will have exactly the same Story Point “size” or estimate exactly the same way. Every team is still unique and has their own dynamic that works for them. You will find, however, that the “size” of each team’s Story Point is close enough to allow for Program and Portfolio level estimating and planning.

This is not intended to take the place of established Agile practices for planning, splitting, and estimating the work that teams deliver. It is intended to get teams started in such a way that planning, splitting, and estimating can be done more simply and effectively across multiple teams. Once you establish your baseline, throw Ideal Man-Days out the window – it then becomes only a part of the criteria for relative estimation, along with complexity and uncertainty. Once you establish your initial velocity, throw the 8 Story Points per person per Sprint out the window – instead, use “yesterday’s weather”, current circumstances, and team growth to determine the number of points the team will commit to each Sprint.


Just like any other tool, metric, practice, meeting, or role that we use in Agile, the practices used for Normalizing Story Points have a stated benefit. We do not do things for the sake of doing them. Normalizing Story Points can have a tremendous positive impact on an organization practicing Agile at scale; a misunderstanding of Normalized Story Points can have a significant negative impact on that same organization.